QuikTrip: Overnight Demo, Next-Morning Pour-Back

QuikTrip: 1,2,3 Concrete project photo 1

Convenience stores never close, so concrete work has to fit into a single night. In May 2022 we completed four QuikTrip remove-and-replace jobs on back-to-back nights, then returned in November for demolition at North 1604/37 and Foster/I-10.

ClientQuikTrip
LocationsSan Antonio, incl. Marbach/1604, North 1604/37, Foster/I-10
DatesMay & November 2022
ScopeOvernight demolition, steel, pour-back

How an overnight cycle works

  • 9 PM: barricade, saw-cut and break out the old concrete
  • Overnight: haul off spoils, prep base, tie steel
  • Morning: pour back and finish (the fourth job poured at 10 AM)
  • Protect and reopen as soon as the concrete allows

Our first QT job was demolished the night of May 8 and poured May 9. The third, at Marbach and 1604, was demolished overnight on May 15. The fourth was demolished at 9 PM on May 16, with steel tied and pour-back at 10 AM on May 17.

This kind of schedule takes our own equipment, an experienced crew and tight coordination with the ready-mix supplier. Talk to us about phasing your site.