100-Yard Custom Home Foundation

100-Yard Custom Home Foundation: 1,2,3 Concrete project photo 1

Written by

in

On May 24, 2021 we poured a 100-yard foundation for a custom home.

DateMay 24, 2021
Volume100 cubic yards
ScopeSoil compaction, beam trenching, forms, steel, place & finish

Two weeks of rain, one big day

Rain came and went for two weeks while we got the site ready:

  • Compacted the soil
  • Trenched the beams
  • Set the forms
  • Tied the steel

Then we placed and finished all 100 yards in a single day with a pump, several trucks and ride-on power trowels.

Building a custom home? Request a foundation quote.

Project photos