H-E-B Lockhart: Phase 1 Paving in a Four-Day Window

H-E-B Lockhart: 1,2,3 Concrete project photo 1

From January 15 through January 18, 2024, our crews completed Phase 1 of concrete work at H-E-B in Lockhart, Texas: demolition through finished paving, with the store open the whole time.

ClientH-E-B
LocationLockhart, TX
DatesJanuary 15–18, 2024
ScopeDemolition, subgrade, steel, paving

The scope

  • Break out and haul off existing concrete
  • Prepare and compact the subgrade
  • Set forms and tie reinforcing steel
  • Place, finish and cure new paving

Working around a live store

Grocery work runs on the shopper’s schedule. We isolated and sequenced each section so customers and deliveries could keep moving while each area was demolished, poured and cured.