  • Silos at Freiheit, New Braunfels: 100 Yards on the Ground

    Silos at Freiheit, New Braunfels: 100 Yards on the Ground

    At the Silos at Freiheit development in New Braunfels, we placed site concrete and sidewalks from fall 2021 into early 2022.

    ProjectSilos at Freiheit
    LocationNew Braunfels, TX
    DatesOctober 2021 – February 2022
    ScopeSite concrete, sidewalks

    A 100-yard day

    On October 27, 2021 we had 100 yards of concrete on the ground in a single placement. A day like that takes a full crew, steady truck spacing and finishers who can keep up.

    Final sidewalks

    In February 2022 we returned to pour the last sections of sidewalk and finish our scope.

    Request a quote for your development.

    Project photos

  • H-E-B Corpus Christi: Night Work and Store Paving

    H-E-B Corpus Christi: Night Work and Store Paving

    We’ve done concrete work at H-E-B stores in Corpus Christi since 2019, including H-E-B Corpus 4 in December 2019 and another store in March 2020.

    ClientH-E-B
    LocationCorpus Christi, TX
    Dates2019–2022

    In March 2022 we returned for a night job, working after hours so the store and parking lot stayed open in the daytime.

    Corpus Christi and the Coastal Bend are part of our regular service area. Request a quote.

    Project photos

  • Selma and Floresville: Two Slabs in One Week

    Selma and Floresville: Two Slabs in One Week

    In February 2022 we built two slabs a week apart, one in Selma and one in Floresville. Each took two days.

    LocationsSelma & Floresville, TX
    DatesFebruary 1–2 and 7–8, 2022
    Concrete3000 PSI, 4 in. thick
    Reinforcement#3 rebar @ 12 in. OCEW
    FinishBroom

    Same spec, done right both times

    • Remove grass and topsoil
    • Set forms to grade
    • Tie #3 rebar at 12 inches on center each way
    • Place 3000 PSI concrete, 4 inches thick
    • Broom finish

    Rebar on a grid at 12 inches each way is the step budget installers skip, and it’s what keeps a slab from breaking apart over time. Get a quote for your slab.

    Project photos

  • 3,000 sq ft Driveway Remove and Replace

    3,000 sq ft Driveway Remove and Replace

    From January 7 to January 12, 2022 we tore out and replaced a 3,000 square foot driveway at a large home.

    Area3,000 sq ft
    DatesJanuary 7–12, 2022
    Concrete3000 PSI, 5 in. thick
    Reinforcement3/8 in. rebar @ 12 in. OCEW
    FinishBroom

    Process

    • Demolish existing driveway and haul off spoils
    • Prep and compact the base
    • Set forms and tie 3/8-inch rebar at 12 inches each way
    • Place 3000 PSI concrete at 5 inches thick
    • Broom finish

    We poured it 5 inches thick instead of the usual 4, which gives it more strength for heavy vehicles and long driveways. Request a quote.

    Project photos

  • Driveway Additions and Back Patios in San Antonio

    Driveway Additions and Back Patios in San Antonio

    Adding on to a driveway or patio is one of our most common residential jobs. Here are three San Antonio projects from 2021.

    LocationSan Antonio, TX
    DatesJune, August & December 2021
    Concrete3000 PSI, 4–5 in. thick
    Reinforcement3/8 in. rebar @ 12 in. OCEW, doweled
    FinishBroom

    Patio, driveway add-on and sidewalk, August 2021

    Over two days we poured a back patio, a driveway add-on and a sidewalk: 3000 PSI concrete, 4 inches thick, with 3/8-inch rebar at 12 inches each way, doweled into the existing concrete.

    Patio with perimeter beam plus driveway extension, June 2021

    For this back patio add-on we poured 5-inch concrete with a perimeter toe beam 12 inches deep by 8 inches wide. We also poured a 4-inch driveway extension, both reinforced at 12 inches each way.

    Driveway and patio addition, December 2021

    We added on to the driveway and back patio with 3/8-inch rebar at 12 inches each way and 4-inch, 3000 PSI concrete.

    Why doweling matters

    When new concrete meets old, we drill into the existing slab and set rebar dowels. That keeps the two slabs from shifting apart and cracking at the joint.

    Get a quote for your addition.

    Project photos

  • Pool Deck Remove and Replace

    Pool Deck Remove and Replace

    In October 2021 we tore out a worn pool deck and poured a new one.

    DateOctober 11, 2021
    Concrete3000 PSI, 4 in. thick
    Reinforcement6-gauge wire mesh
    FinishBroom
    • Remove existing deck without damaging the pool
    • Prep base and place 6-gauge wire mesh
    • Pour 3000 PSI concrete, 4 inches thick
    • Broom finish for wet-foot traction

    Pool decks get wet, sun-baked and hosed down all the time. Getting slopes away from the pool and a slip-resistant finish matters as much as strength. Request a quote.

    Project photos

  • Driveway Extensions and Sidewalks: San Antonio, Schertz and Windcrest

    Driveway Extensions and Sidewalks: San Antonio, Schertz and Windcrest

    Three residential jobs from 2021, each built to the same standard.

    LocationsSan Antonio, Schertz, Windcrest
    DatesJuly–December 2021
    Concrete3000 PSI, 4–5 in.
    Reinforcement3/8 in. rebar @ 12 in. OCEW

    Driveway extension and walkway, San Antonio

    In December 2021 we poured 5-inch, 3000 PSI concrete over 3/8-inch rebar with a broom finish.

    Sidewalk and driveway add-on, Schertz

    In August 2021 we poured 4-inch, 3000 PSI concrete with rebar at 12 inches each way, doweled into the existing patio.

    New sidewalk, Windcrest

    In July 2021 we poured a sidewalk to the same spec, doweled into the existing patio for a tight, lasting connection.

    Request a quote.

    Project photos

  • Parker Place, La Vernia: Detention and Retention Pond Slabs

    Parker Place, La Vernia: Detention and Retention Pond Slabs

    For the Parker Place development in La Vernia, we built the concrete for the water retention and detention pond.

    ProjectParker Place
    LocationLa Vernia, TX
    DatesNovember 18 – December 2, 2021
    ScopeRetention pond slab, detention pond

    Phase 1 of the retention pond slab went in November 18–19, 2021. The detention pond was 100% complete on December 2, 2021.

    Pond slabs are poured on slopes and have to handle moving water, so forming, reinforcement and finishing take different methods than flat paving.

    See our heavy civil work or request a quote.

    Project photos

  • TxDOT Sealy: Passed Every Inspection

    TxDOT Sealy: Passed Every Inspection

    We started a TxDOT job in Sealy on August 30, 2021.

    AgencyTxDOT
    LocationSealy, TX
    DatesAugust 30 – September 2021
    ResultPassed TxDOT and third-party inspection

    Building up the base

    The job needed a tall compacted A2 base pad. By September 23 we were 6 feet up, with 3 more to go.

    Inspection-ready

    On September 16 we tied steel. The forms, embeds and reinforcement passed both TxDOT inspection and the third-party inspection, and the pour was set for September 17.

    Passing on the first try keeps agency schedules on track. Send us your TxDOT or agency bid.

    Project photos

  • Lock Away Storage, Culebra Road: Apron Replacement

    Lock Away Storage, Culebra Road: Apron Replacement

    On August 24, 2021 we removed and replaced a concrete apron at Lock Away Storage on Culebra Road.

    ClientLock Away Storage
    LocationCulebra Rd, San Antonio
    DateAugust 24, 2021
    ScopeApron remove and replace

    Aprons carry turning trucks and trailers every day. A failed one is a hazard and a liability. We sectioned the work so tenants kept access to their units.