Parker Place, La Vernia: Detention and Retention Pond Slabs

Parker Place, La Vernia: 1,2,3 Concrete project photo 1

Written by

in

For the Parker Place development in La Vernia, we built the concrete for the water retention and detention pond.

ProjectParker Place
LocationLa Vernia, TX
DatesNovember 18 – December 2, 2021
ScopeRetention pond slab, detention pond

Phase 1 of the retention pond slab went in November 18–19, 2021. The detention pond was 100% complete on December 2, 2021.

Pond slabs are poured on slopes and have to handle moving water, so forming, reinforcement and finishing take different methods than flat paving.

See our heavy civil work or request a quote.