  • Laughlin AFB Main Entrance Road: 8-Inch Concrete Reconstruction, Phase 1

    Laughlin AFB Main Entrance Road: 8-Inch Concrete Reconstruction, Phase 1

    The main commercial entrance to Laughlin Air Force Base carries delivery trucks, contractors and base traffic every day. 1,2,3 Concrete is on site in Del Rio, Texas, rebuilding this entrance road in phases, from subgrade preparation through final grade and the 8-inch concrete pour. Phase 1 covers 600 linear feet, 12 feet wide.

    ProjectMain commercial entrance road reconstruction, Phase 1
    LocationLaughlin Air Force Base, Del Rio, TX
    Phase 1 size600 linear feet x 12 feet wide
    Concrete section8-inch thick concrete
    Base materialA2 base material
    Work performedBase material hauling and placement, elevation verification, trimming to final grade, concrete placement
    SettingActive base entrance, phased work with traffic control in place
    StatusIn progress (photos dated October 27, 2026)

    Scope of work

    A2 base material. Base material is hauled in, staged and spread to build a stable, uniform layer under the new concrete. Consistent base thickness is what keeps a roadway slab from settling and cracking under heavy truck traffic.

    Elevation control. Before concrete is placed, grade elevations are checked and marked on the base with green layout paint. The marks in the photos show the depth remaining to the finished surface, so the crew knows exactly how much to remove or add to reach a true 8-inch slab. On this project the base ran 1-1/2 inches high in places and was trimmed back to design grade before the pour.

    Working beside existing infrastructure. The work runs tight against the existing concrete roadway and a concrete drainage channel, so equipment is sized to trim and shape the base without disturbing either.

    Concrete placement. Once the base passes elevation checks, the section is set up and the 8-inch concrete is placed.

    Traffic control and safety. Barrels and a defined work zone separate crews and equipment from live traffic. Ground crews work in high-visibility PPE and hard hats, and a spotter works with the operators during loading.

    Equipment on this project

    • Compact tracked excavator (CAT): trimming, shaping and cleanup against the existing roadway and the drainage channel
    • Wheel loader: loading and moving A2 base material, with a ground spotter directing the work
    • Skid steer with bucket: hauling and spreading material in tight sections of the roadway
    • Hand crews: shovel work, grade checks and layout marking

    What this project shows agencies and prime contractors

    • Our own equipment and crews: excavators, loaders, skid steers, rollers, buggies and trailers, so schedule and quality are in our hands
    • Active-site experience: phased work at a live base entrance with traffic control in place
    • Quality control before concrete: elevation verified and corrected on the base, not after the pour
    • Track record: 28 years of concrete experience, with work for State and Federal offices, H-E-B, Tesla and SpaceX
    • Statewide reach: we install concrete all over Texas, from high-end residential to large commercial, industrial and infrastructure projects

    Project photos

    Frequently asked questions

    Does 1,2,3 Concrete work on military bases and federal sites? Yes. We are currently working on the main commercial entrance road at Laughlin Air Force Base in Del Rio, and we have completed work for State and Federal offices.

    Do you provide your own equipment? Yes. We run our own excavators, loaders, skid steers, rollers, buggies, trailers and crews.

    What concrete thickness is used on this roadway? Thickness is set by the project design. This Laughlin project uses an 8-inch concrete section over A2 base.

    Do you work outside San Antonio? Yes. We install concrete all over Texas.

    Do you do asphalt work? No. We specialize in concrete and concrete demolition.

  • Uresti Tax Office: Sidewalk Remove-and-Replace

    Uresti Tax Office: Sidewalk Remove-and-Replace

    In April 2026 our crew prepped and poured new concrete at the Uresti tax office, a busy public building where people come and go all day.

    LocationSan Antonio, TX
    Pour dateApril 2026
    ScopeDemolition, forming, steel, pour-back

    Scope

    • Saw-cut and break out the failed sidewalk and entry concrete
    • Haul off debris and prep the subgrade
    • Set forms and reinforcing steel
    • Place, finish and cure new concrete

    Public buildings can’t shut down for construction. We sectioned the work so visitors always had a clear, safe way in, and we left the site clean at the end of every shift.

    Government and agency projects are one of our core practice areas. See our public and government capabilities or request a quote for your facility.

    Project photos

  • Wells Fargo: New Sidewalks and Main-Entrance ADA Ramp

    Wells Fargo: New Sidewalks and Main-Entrance ADA Ramp

    Just before Christmas 2024 we finished new sidewalks and a handicap ramp at the main entrance of a Wells Fargo branch.

    ClientWells Fargo
    CompletedDecember 23, 2024
    ScopeSidewalks, ADA ramp at main entrance

    Getting ADA work right

    Accessible ramps leave little room for error. Slope, cross-slope, landing size and transitions all have to meet ADA requirements, or the work gets torn out and redone. We form and check every ramp before the truck shows up.

    • Remove existing walks at the entrance
    • Form new sidewalks and the ramp to ADA slopes
    • Pour directly from the ready-mix truck
    • Broom finish for slip resistance

    Banks, offices and retail centers call us for ADA upgrades. Request a quote for your property.

    Project photos

  • TxDOT Cotulla: Agency Concrete Pour

    TxDOT Cotulla: Agency Concrete Pour

    On September 21, 2023 we poured concrete for the Texas Department of Transportation in Cotulla.

    AgencyTxDOT
    LocationCotulla, TX
    Pour dateSeptember 21, 2023

    TxDOT work is held to strict specifications. Steel placement, cover, mix design and finishing are all inspected before and during the pour. Our crews have passed TxDOT and third-party inspections on maintenance facility work across the state.

    Read about our TxDOT Sealy project, or send us your bid documents.

    Project photos

  • TxDOT Maintenance Facility: Wash-Out Pit

    TxDOT Maintenance Facility: Wash-Out Pit

    On June 23, 2023 we were formed, tied and ready to pour a wash-out pit at a TxDOT maintenance facility.

    AgencyTxDOT
    Pour dateJune 23, 2023
    StructureWash-out pit

    Wash-out pits take abuse every day from equipment, water and sediment. Walls and slab are reinforced and formed as one system, with careful attention to drainage slopes and joints so the structure holds up for years.

    We build pits, pads and specialty structures for public and industrial clients. Request a quote.

  • San Antonio River Authority Project

    San Antonio River Authority Project

    On September 7, 2022 our crew completed concrete work for the San Antonio River Authority.

    AgencySan Antonio River Authority
    DateSeptember 7, 2022

    Public agencies like SARA need contractors who meet specifications, document their work and keep the site safe and orderly. Those habits carry over to every project we take on.

    See more public and government work or send us your bid package.

    Project photos

  • TxDOT Sealy: Passed Every Inspection

    TxDOT Sealy: Passed Every Inspection

    We started a TxDOT job in Sealy on August 30, 2021.

    AgencyTxDOT
    LocationSealy, TX
    DatesAugust 30 – September 2021
    ResultPassed TxDOT and third-party inspection

    Building up the base

    The job needed a tall compacted A2 base pad. By September 23 we were 6 feet up, with 3 more to go.

    Inspection-ready

    On September 16 we tied steel. The forms, embeds and reinforcement passed both TxDOT inspection and the third-party inspection, and the pour was set for September 17.

    Passing on the first try keeps agency schedules on track. Send us your TxDOT or agency bid.

    Project photos

  • Hollywood Park Police Station

    Hollywood Park Police Station

    On July 16, 2021 our crew completed concrete work at the Hollywood Park police station.

    ClientTown of Hollywood Park
    FacilityPolice station
    DateJuly 16, 2021

    Public-safety buildings run 24 hours a day. We kept emergency access open throughout and coordinated the work with department staff.

    More public projects · Request a quote

    Project photos

  • Evans Road Sidewalk Expansion

    Evans Road Sidewalk Expansion

    We built new sidewalk along Evans Road as part of a sidewalk expansion project.

    ProjectEvans Road Sidewalk Expansion
    LocationSan Antonio, TX
    DateSpring 2021

    Right-of-way work means traffic control, grades that tie into existing driveways and curbs, and accessible routes for pedestrians.

    Request a quote.

    Project photos

  • Texas DPS Office, Uvalde: ADA Access and Sidewalks

    Texas DPS Office, Uvalde: ADA Access and Sidewalks

    On April 27, 2021 we completed ADA-compliant access improvements at the Texas DPS office in Uvalde, including a handicap ramp and new sidewalks.

    AgencyTexas Department of Public Safety
    LocationUvalde, TX
    DateApril 27, 2021
    ScopeADA-compliant access ramp, sidewalks

    Scope

    • Form ramp and walks to ADA slope requirements
    • Pour from the ready-mix truck
    • Finish and joint new sidewalks

    State facilities have to meet accessibility rules exactly. Send us your agency project.