Selma and Floresville: Two Slabs in One Week

Selma and Floresville: 1,2,3 Concrete project photo 1

Written by

in

In February 2022 we built two slabs a week apart, one in Selma and one in Floresville. Each took two days.

LocationsSelma & Floresville, TX
DatesFebruary 1–2 and 7–8, 2022
Concrete3000 PSI, 4 in. thick
Reinforcement#3 rebar @ 12 in. OCEW
FinishBroom

Same spec, done right both times

  • Remove grass and topsoil
  • Set forms to grade
  • Tie #3 rebar at 12 inches on center each way
  • Place 3000 PSI concrete, 4 inches thick
  • Broom finish

Rebar on a grid at 12 inches each way is the step budget installers skip, and it’s what keeps a slab from breaking apart over time. Get a quote for your slab.