We started a TxDOT job in Sealy on August 30, 2021.
| Agency | TxDOT |
| Location | Sealy, TX |
| Dates | August 30 – September 2021 |
| Result | Passed TxDOT and third-party inspection |
Building up the base
The job needed a tall compacted A2 base pad. By September 23 we were 6 feet up, with 3 more to go.
Inspection-ready
On September 16 we tied steel. The forms, embeds and reinforcement passed both TxDOT inspection and the third-party inspection, and the pour was set for September 17.
Passing on the first try keeps agency schedules on track. Send us your TxDOT or agency bid.