For the Parker Place development in La Vernia, we built the concrete for the water retention and detention pond.
| Project | Parker Place |
| Location | La Vernia, TX |
| Dates | November 18 – December 2, 2021 |
| Scope | Retention pond slab, detention pond |
Phase 1 of the retention pond slab went in November 18–19, 2021. The detention pond was 100% complete on December 2, 2021.
Pond slabs are poured on slopes and have to handle moving water, so forming, reinforcement and finishing take different methods than flat paving.