  • San Marcos Outlets: Overnight Storefront Walkway Pour

    San Marcos Outlets: Overnight Storefront Walkway Pour

    On January 15, 2026 we poured a section of the covered storefront walkway at the San Marcos outlets. We set steel and placed concrete after hours so the stores could stay open.

    LocationSan Marcos, TX
    Pour dateJanuary 15, 2026
    ScopeCovered storefront walkway, rebar, night pour

    Retail concrete without the disruption

    Outlet centers depend on foot traffic. Night work lets us cut out old concrete, tie a fresh rebar mat and pour under lights, so shoppers find finished, barricaded sections the next morning instead of an active jobsite.

    • Rebar grid tied on chairs for proper cover
    • Concrete placed and screeded under temporary lighting
    • Edges finished tight to storefronts and columns
    • Area protected while it cures

    Planning work at a shopping center or retail property? Send us your scope. Night and weekend schedules are standard for us.

    Project photos

  • H-E-B San Marcos: 8-Inch, 4000 PSI Drive and Parking Replacement

    H-E-B San Marcos: 8-Inch, 4000 PSI Drive and Parking Replacement

    In summer 2021 we replaced drive and parking lot concrete at H-E-B San Marcos in phases, starting in June and finishing on July 10.

    ClientH-E-B (San Marcos 01)
    LocationSan Marcos, TX
    DatesJune–July 2021
    Concrete4000 PSI, 8 in. thick
    Reinforcement#4 rebar @ 12 in. OCEW
    FinishBroom

    Built for heavy traffic

    • Remove and replace existing paving
    • 8-inch thick, 4000 PSI concrete
    • #4 rebar at 12 inches on center each way
    • Broom finish

    Phasing let the store keep most of its parking open while each section was demolished, poured and cured.

    Request a quote for your parking lot.