Convenience stores never close, so concrete work has to fit into a single night. In May 2022 we completed four QuikTrip remove-and-replace jobs on back-to-back nights, then returned in November for demolition at North 1604/37 and Foster/I-10.
| Client | QuikTrip |
| Locations | San Antonio, incl. Marbach/1604, North 1604/37, Foster/I-10 |
| Dates | May & November 2022 |
| Scope | Overnight demolition, steel, pour-back |
How an overnight cycle works
- 9 PM: barricade, saw-cut and break out the old concrete
- Overnight: haul off spoils, prep base, tie steel
- Morning: pour back and finish (the fourth job poured at 10 AM)
- Protect and reopen as soon as the concrete allows
Our first QT job was demolished the night of May 8 and poured May 9. The third, at Marbach and 1604, was demolished overnight on May 15. The fourth was demolished at 9 PM on May 16, with steel tied and pour-back at 10 AM on May 17.
This kind of schedule takes our own equipment, an experienced crew and tight coordination with the ready-mix supplier. Talk to us about phasing your site.